For the best experience, open
https://m.greaterkashmir.com
on your mobile browser.

Mughal Road opening may get delayed

Snow slides affect snow clearance work
02:37 AM Mar 28, 2024 IST | Sumit Bhargav
mughal road opening may get delayed
Advertisement

Rajouri, Mar 27: Small snow slides that occurred during the last 24 hours partially affected the ongoing snow clearance operation on the Mughal Road with 300 meters of road stretch cleared on Wednesday and a 1 km stretch now pending to reach Pir Ki Gali from Poonch side.

Advertisement
   

The snow clearance work by the Mechanical Engineering Department is ongoing and 42.3 km of road from Bufliyaz side was cleared till Tuesday evening.

Advertisement

Assistant Engineer in the Mechanical Engineering Department, Tariq Ahmad told Greater Kashmir that many small slides occurred on the road in the last 2 km stretch at PKG side and the deployed machinery cleared these slides due to which only 300 meters of road stretch had been cleared on Wednesday.

Advertisement

He said that now 1 km of road stretch is pending to reach Pir Ki Gali.

Advertisement

Ahmad said that fresh rainfall started in the area on Wednesday evening and work was expected to be affected if the rainfall continued.

Advertisement

Talking to Greater Kashmir, Executive Engineer Mughal Road Projects, Shokat Ali said that the Mechanical Engineering Department was carrying out the work but fresh rainfall had started on Wednesday evening.

Advertisement

“Although we are expecting the restoration of the road by the month's end, there is a forecast of rainfall in the next few days and heavy rainfall can cause some delay in restoration,” he said.

Advertisement

Advertisement
×